2010  ADOPTED SIX-YEAR PLAN

                                                             CONCRETE ROADS

PROJECT NO.

     ROAD NO.

IMPROVEMENT

  LENGTH

    COST

     FUNDING

C89(20)B

P32/32 WEST OF 39

CONCRETE

1.2 MILES

1,118,000

FEDERAL AID

 

C89(202)

32 EAST OF H133

CONCRETE

2.0 MILES

1,886,000

FEDERAL AID

 

                                                                                   

                                                                                                               SUB-TOTAL:          $3,004,000.00

 

 

                                                                     2010  ADOPTED SIX-YEAR PLAN

                                                    ASPHALT ROADS & ARMOR COAT

PROJECT NO.

     ROAD NO.

IMPROVEMENT

  LENGTH

    COST

     FUNDING

C89(466)

30 BET 7 & 5

7 BET 30 & 28

ASPHALT

1.0 MILES

100,000

COUNTY   

C89(467)

15    BET HWY 91 & HWY 30

ASPHALT

6.0 MILES

600,000

COUNTY

C89(470)

9     BET HWY 30 & 26

ASPHALT

4.0 MILES

400,000

COUNTY

C89(471)

 

P35   BET P28 & P32

ASPHALT

3.5 MILES

350,000

COUNTY

C89(509)

29 BET P30 & 34

ARMOR COAT

1.5 MILES

35,000

COUNTY

C89(520)

12  BET 7 & COUNTY LINE

ASPHALT

3.0 MILES

300,000

COUNTY

                                                                   SUB-TOTAL:      $1,785,000.00 

                 

                                                         2010 ADOPTED SIX-YEAR PLAN

                                                   BRIDGES & BOX CULVERT PROJECTS

PROJECT NO.

     ROAD NO.

  IMPROVEMENT

  LENGTH

    COST

     FUNDING

C89(223)

P26 DESOTA

BRIDGE

0.5 MILES

544,000

FEDERAL-AID

 

C89(242)

24 BET 25 & 27

ROW PENDING

BOX-CULVERT

0.5 MILES

513,000

FEDERAL-AID

 

C89(269)

P43 NORTH

OF CALHOUN

BRIDGE

0.2 MILES

406,000

FEDERAL-AID

C89(270)

28 BET 7 & 9

 

BRIDGE

0.1 MILES

150,000

SOFT-MATCH

COUNTY FUNDING

C89(354)

30 BET P19 & 21

BRIDGE

0.2 MILES

200,000

SOFT-MATCH

COUNTY FUNDING

C89(356)

6 EAST OF RD 5

BOX-CULVERT

0.2 MILES

100,000

SOFT-MATCH

COUNTY FUNDING

C89(357)

D/H RD S/W CORNER   

BRIDGE

0.3 MILES

300,000

FEDERAL-AID

C89(358)

P33 NORTH OF BLAIR

BRIDGE(JEO DESIGN)

0.1 MILES

448,000

FEDERAL-AID

C89(414)

24 BET 21 & 23

BRIDGE

0.1 MILES

170,000

SOFT-MATCH

COUNTY FUNDING

C89(456)

25 BET HWY 91 & 22

REPLACE LESS THAN 20 FT BRIDGE

.01 MILES

150,000

COUNTY

C89(458)

P10 BET 9 & 11

REPLACE LESS THAN 20 FT BRIDGE

0.1 MILES

75,000

COUNTY

C89(486)

COUNTY ROAD “A”

BURT-WASH LINE

BOX-CULVERT

0.1 MILES

225,000

SOFT MATCH

COUNTY FUNDING

C89(487)

 

24 BET P11 & 13

BRIDGE

0.1 MILES

250,000

SOFT MATCH COUNTY FUNDING

 

                                                                             SUB-TOTAL:     $3,531,000.00

 

                                                      2010 ADOPTED SIX YEAR PLAN

                                   GRADING & STAGE CONSTRUCTION PROJECTS

 

PROJECT NO.

      ROAD NO.

  IMPROVEMENT

  LENGTH

    COST

     FUNDING

C89(216)

37 SOUTH OF Hwy 75 OLD DUMP HILL

GRADING/STAGE CONSTRUCTION

0.7 MILES

300,000

COUNTY

C89(238)

P33    BET ROAD P14

ROAD 33

STAGE CONSTRUCTION

3.2 MILES

100,000

COUNTY

C89(276)

11 NORTH OF ARLINGTON

STAGE CONSTRUCTION

6.0 MILES

150,000

COUNTY

C89(302)

26     BET

27 & 29

GRADING & WIDEN ROAD       

1.0 MILES

150,000

COUNTY

C89(342)

31   BET P30 & DUTCH HALL

STAGE CONSTRUCTION

5.5 MILES

270,000

COUNTY

C89(345)

34      BET

CALHOUN & P34

STAGE CONSTRUCTION

1.5 MILES

90,000

COUNTY

C89(346)

28     BET

3 & 9

STAGE CONSTRUCTION

2.5 MILES

150,000

COUNTY

C89(347)

P16    BET

HWY 75 & 27

STAGE CONSTRUCTION

2.0 MILES

120,000

COUNTY

C89(348)

26    BET

21 & 27

STAGE CONSTRUCTION

3.0 MILES

180,000

COUNTY

C89(349)

P26 & P33   BET HWY

133 & P35

STAGE CONSTRUCTION

2.0 MILES

200,000

COUNTY

C89(360)

P40   BET 

HWY 75 & 49

STAGE CONSTRUCTION

1.50 MILES

60,000

COUNTY &

TWP #1

C89(361)

38    BET

37 & 39

STAGE CONSTRUCTION

1.0 MILES

55,000

COUNTY &

TOWNSHIP #1

C89(362)

36   BET

37 & 39

STAGE CONSTRUCTION

1.0 MILES

55,000

COUNTY &

TOWNSHIP #1

C89(436)B

39 BET P32 & P28

STAGE  CONSTRUCTION

2.0 MILES

200,000

COUNTY

C89(437)B

P39 BET P32 & 28

STAGE CONSTRUCTION

1.5 MILES

150,000

COUNTY

C89(441)

 

5   BET

28 & 30

STAGE CONSTRUCTION

1.2 MILES

55,000

COUNTY

C89(442)

 

7   BET  HWY 91 &

HERMAN-SCRIBNER

STAGE CONSTRUCTION

9.0 MILES

270,000

COUNTY

C89(443)

 

TIMBER CREEK & NORTH RIDGE RD.

SOUTH OF 30 (ROLLING ACRES)

1.5 MILES

50,000

LANDOWNERS

C89(444)B

40  BET SPRING

VALLEY & HWY 75

STAGE CONSTRUCTION

1.0 MILES

100,000

COUNTY &

TOWNSHIP #1

C89(473)

 

  21 BET RD P4 & 4

GRADING & IMPROVEMENT

1.0 MILES

25,000

COUNTY

C89(474)B

26 BET 7 & 15

GRADING & IMPROVEMENTS

3.0 MILES

75,000

COUNTY

 

C89(475)

P15 BET 38 & DUTCH HALL ROAD

GRADING/STAGE CONSTRUCTION

2.5 MILES

150,000

COUNTY

C89(476)

33 BET DUTCH HALL ROAD & 40

STAGE CONSTRUCTION

1.0 MILES

25,000

COUNTY

C89(477)

LOOKING GLASS HILLS

STAGE CONSTRUCTION

1.5 MILES

100,000

COUNTY

C89(495)

 

P3 BET HWY 91 & 20

GRADING & ROAD CONSTRUCTION

1.25 MILES

 30,000

COUNTY

C89(498)

 

COUNTY ROAD 14 & 35

NORTH OF P14

GRADING & ROAD CONSTRUCTION

1.00 MILES

25,000

COUNTY

C89(514)

COUNTY ROAD NO. 41 & P28 BET CO. RD P26 & HIGHWAY 75

STAGE CONSTRUCTION

1.3 MILES

75,000

COUNTY

& TOWNSHIP #2

C89(519)

51 FROM P38 TO P40

STAGE CONSTRUCTION

1.0 MILES

25,000

COUNTY

C89(523)

38 BET P43 & P41

STAGE CONSTRUCTION

1.0 MILES

25,000

COUNTY

                                                                                    SUB-TOTAL:          $3,360,000.00

 

 

 

GRAND TOTAL FOR ALL CATEGORIES:                       $11,680,000.00