ADOPTED ONE-YEAR PLAN
FOR ASPHALT ROADS
| PROJECT NO. | ROAD NO. | IMPROVEMENT | LENGTH | COST | FUNDING |
| C89(363) | 37 bet
Pioneer Rd. & H133 |
ASPHALT | 2.8 MILES | 450,000
(75,000) |
COUNTY/ TWP #1
& HOFER (3) |
| C89(391) | 9 bet
H91 & 26 |
ASPHALT | 2.0 MILES | 150,000 | COUNTY
|
| C89(401) | P39
North of P32 |
ASPHALT | .05 MILES | 118,350 | DEVELOPER
|
| C89(402) | 39
North of P32 |
ASPHALT | 1.0 MILES | 273,400 | DEVELOPER |
| C89(403) | 29 South of Hwy 30 | ASPHALT | 0.2 MILES | 65,000
(15,000) |
COUNTY & DEVELOPER |
SPECIAL SAFETY PROJECT
| PROJECT NO. | ROAD NO. | IMPROVEMENT | LENGTH | COST | FUNDING |
| C89(400) | 39
South of P32 |
LENGTHEN CMPS,
REMOVE TREES, & OTHER ITEMS |
0.2 MILES | 76,000 | FEDERAL
SAFETY FUNDING |
BRIDGES & BOX CULVERTS
| PROJECT NO. | ROAD NO. | IMPROVEMENT | LENGTH | COST | FUNDING |
| C89(221) | 31 Bet
38 & 40 |
BRIDGE | 0.2 MILES | 350,000 | FEDERAL-AID
IN PROGRESS |
| C89(239) | DUTCH HALL ROAD West
of Hwy 133 |
BRIDGE | 0.5 MILES | 200,000 | FEDERAL-AID
COST SHARE W/ DOUGLAS CO. |
| C89(243) | 20 Bet
9 & P11 |
BRIDGE | 0.1 MILES | 330,000 | FEDERAL-AID
|
| C89(351) | 16 just west of Road 3 | BOX-CULVERT | 0.1 MILES | 60,000 | SOFT MATCH FUNDING |
| C89(352) | 21 Bet
D.H. & P38 |
BRIDGE | 0.1 MILES | 80,000 | SOFT MATCH FUNDING |
| C89(353) | 38 Bet
31 & 33 |
BRIDGE | 0.1 MILES | 225,000 | SOFT-MATCH
FUNDING |
| |
ADOPTED ONE-YEAR PLAN
FOR GRADING & STAGE CONSTRUCTION PROJECTS
| PROJECT NO. | ROAD NO. | IMPROVEMENT | LENGTH | COST | FUNDING |
| C89(296) | ROLLING ACRES | GRADING/STAGE CONSTRUCTION | 1.5 MILES | 50,000 | COUNTY |
| C89(301) | P33 Bet
Blair & P14 |
GRADING/STAGE CONSTRUCTION | 2.0 MILES | 100,000 | COUNTY |
| C89(364) | COUNTRY-LAND | GRADING/STAGE CONSTRUCTION | 0.8 MILES | 20,000 | COUNTY & LANDOWNERS |
| C89(390) | 31 Bet 36 & 40 | STAGE CONSTRUCTION | 2.0 MILES | 50,000 | COUNTY DELAYED 2005 |
| C89(395) | 3 Bet 10 & 12 | GRADING UP ROAD | 1.0 MILES | 25,000 | COUNTY DELAYED 2005 |
| C89(396) | 15 Bet Burt Co. & P2 | GRADING-UP ROAD | .0.5 MILES | 13,000 | COUNTY DELAYED 2005 |
| C89(397) | 19 Bet 16 & 18 | GRADING-UP ROAD | 1.0 MILES | 25,000 | COUNTY DELAYED 2005 |
| C89(398) | 14 Bet 23 & 25 | GRADING-UP ROAD | 1.0 MILES | 19,000 | COUNTY DELAYED 2005 |
| C89(405) | P29 South
of 29(Kubie) |
STAGE CONSTRUCTION | 0.7 MILES | 35,000 | COUNTY |
| C89(408) | P26 & P33
Bet H133/H75 |
STAGE CONSTRUCTION | 2.0 MILES | 50,000 | COUNTY |
| C89(409) | P41 North of P38 | GRADING-UP ROAD | 1.0 MILES | 35,000 | COUNTY |
| C89(412)
|
28 Bet 5 & 7 | GRADING-UP ROAD | 1.0 MILES | 25,000 | COUNTY |
| C89(413) | 29 Bet 30 & 36 | GRADING-UP ROAD | 3.0 MILES | 65,000 | COUNTY |
ADOPTED ONE-YEAR PLAN
FOR ARMOR COAT PROJECTS
| PROJECT NO. | ROAD NO. | IMPROVEMENT | LENGTH | COST | FUNDING |
| C89(339) | P40 West of P51 | ARMOR COAT | 0.5 MILES | $8,000 | COUNTY |
| C89(340) | 40 Bet 45 & S.V. | ARMOR COAT | 0.5 MILES | $8,000 | COUNTY & Twp #1 |
| C89(341) | SPRING VALLEY | ARMOR COAT | 1.3 MILES | $16,000 | COUNTY & LANDOWNERS |
| C89(343) | 14 Bet Hwy 75 & 25 | ARMOR COAT | 2.0 MILES | $28,000 | COUNTY |
| C89(359) | 32 West of P43 | ARMOR COAT | 0.5 MILES | $8,000 | COUNTY & LANDOWNERS |
| C89(365) | 30 & 7
Bet 5 & 9 |
ARMOR COAT | 2.0 MILES | $28,000 | COUNTY & LANDOWNERS |
| C89(386)
|
P30 East of Hwy 75 | ARMOR COAT | 0.7 MILES | $10,000 | COUNTY & RINKERS |
| C89(404) | 30 West of H75 | ARMOR COAT | 1.0 MILES | $14,000 | COUNTY |
| C89(406) | 39 Bet 36 & P38 | ARMOR COAT | 1.5 MILES | $21,000 | COUNTY |